8月15日晚9點,經過五天五夜的鏖戰,南京浦(pu)口(kou)水廠深度處(chu)理工程V型濾池至新(xin)清水池DN1400進水管道(dao)提(ti)前3小時成(cheng)功接駁,并(bing)于16日上午8點30分順利并(bing)網。
該工(gong)(gong)(gong)(gong)程是南(nan)京市一項(xiang)重(zhong)點民生工(gong)(gong)(gong)(gong)程,工(gong)(gong)(gong)(gong)期短、任務重(zhong),加(jia)之施(shi)工(gong)(gong)(gong)(gong)場地狹小、極(ji)端天氣(qi)影響不斷,項(xiang)目(mu)(mu)(mu)面臨工(gong)(gong)(gong)(gong)期壓力巨大。為(wei)保證(zheng)(zheng)水(shui)廠能夠正常(chang)供(gong)水(shui),項(xiang)目(mu)(mu)(mu)部不等不靠(kao)、主動出擊,積極(ji)與各方溝通協調,倒排工(gong)(gong)(gong)(gong)期計(ji)劃(hua),下雨搶(qiang)工(gong)(gong)(gong)(gong)、夜間搶(qiang)險(xian),緊密圍繞“8.15通水(shui)目(mu)(mu)(mu)標”,迅速形成(cheng)大干態(tai)勢。由(you)于地下管(guan)線較為(wei)復雜,且生產管(guan)線切換(huan)施(shi)工(gong)(gong)(gong)(gong)需(xu)在保證(zheng)(zheng)廠區不停產的(de)情況下進(jin)行,項(xiang)目(mu)(mu)(mu)部聯合建設(she)單(dan)位、設(she)計(ji)單(dan)位、監理單(dan)位,詳細劃(hua)分(fen)各道(dao)工(gong)(gong)(gong)(gong)序,現(xian)場反(fan)復實(shi)地測(ce)量模擬,精確計(ji)算工(gong)(gong)(gong)(gong)程量。為(wei)管(guan)道(dao)能夠順利接駁,施(shi)工(gong)(gong)(gong)(gong)過程中項(xiang)目(mu)(mu)(mu)主要管(guan)理人員緊盯現(xian)場,靠(kao)前指(zhi)揮,及(ji)時(shi)指(zhi)導解決問題。此次V型濾池(chi)(chi)至新清水(shui)池(chi)(chi)DN1400進(jin)水(shui)管(guan)連通運行消除了老清水(shui)池(chi)(chi)的(de)滲漏隱(yin)患,為(wei)水(shui)廠的(de)正常(chang)供(gong)水(shui)提供(gong)了堅實(shi)保障,同時(shi)為(wei)項(xiang)目(mu)(mu)(mu)的(de)后期施(shi)工(gong)(gong)(gong)(gong)奠定了堅實(shi)基礎。