3月22日,姜堰城區污水(shui)處理廠提標(biao)、擴建改造工(gong)程(cheng)項目南區生化池(chi)東倉01主體結構(gou)提(ti)前5天完(wan)成砼(tong)澆筑(zhu)任務,為后續“4·30”順利通(tong)水(shui)按下了“快進鍵”。
據(ju)悉,南區生(sheng)化池(chi)01單體是(shi)通過局部(bu)拆除改造原水解(jie)池內隔墻、新建(jian)導流墻及頂板(ban)等措施,將原水(shui)解池改(gai)造為生化池01,其單體(ti)尺(chi)寸為長(chang)度(du)106.5m、寬度(du)34.9m、高度(du)7.65m,模板(ban)面積達到16530㎡,滿堂腳手架體積為28400m3,混凝土用量(liang)(liang)為1542m3,鋼(gang)筋總量(liang)(liang)為241.5t。
項(xiang)目(mu)部自開(kai)工(gong)(gong)以來,迅速投入建設,緊(jin)抓年(nian)度目(mu)標,以“開(kai)局即決(jue)戰(zhan)、起步即沖刺”的(de)姿態(tai)迎(ying)難而(er)上。面對(dui)施(shi)(shi)工(gong)(gong)場地狹小(xiao)、周邊區域交(jiao)錯(cuo)、空(kong)間受限(xian)等困難,項(xiang)目(mu)部優(you)化(hua)施(shi)(shi)工(gong)(gong)方案,強化(hua)現場管理,實施(shi)(shi)交(jiao)叉作(zuo)業(ye),確保(bao)各項(xiang)工(gong)(gong)作(zuo)按計劃(hua)高效推進。同時,針對(dui)工(gong)(gong)期緊(jin)張、需(xu)同步推進南北區施(shi)(shi)工(gong)(gong)的(de)挑戰(zhan),項(xiang)目(mu)部倒排工(gong)(gong)期、細(xi)化(hua)節(jie)點,每日召開(kai)碰頭會梳理工(gong)(gong)作(zuo)進展(zhan),動態(tai)調整施(shi)(shi)工(gong)(gong)計劃(hua),確保(bao)施(shi)(shi)工(gong)(gong)有序高效開(kai)展(zhan)。